 |
 |
 |
 |














 |
|
PARLBY CREEK-BUFFALO LAKE WATER
MANAGEMENT SYSTEM
OPERATIONS PLAN
BUFFALO LAKE
MANAGEMENT TEAM
JANUARY 2002
INTRODUCTION
The Parlby
Creek-buffalo Lake Water Management Project is located in central Alberta,
approximately 70 kms east of Red Deer. The project is an initiative of Albert
Environment to stabilize the water levels in Buffalo Lake. The water
management system has been developed in several stages commencing in 1985.
Portions of the system have been operational for several years with testing
and commissioning occurring since 1987. All phases of construction were
completed in 2000/01, except for some mitigation projects.
In 1992, an
Interim License under the Water Resources Act was granted for the diversion
of water from the Red Deer River to stabilize Buffalo Lake within its
historic lake levels. One of the conditions of the license is the
development of an operational strategy for the Project.
The
Operations Plan for the Parlby Creek-Buffalo Lake Water Management Project
will guide the future management and Operation of the project, in accordance
with the Interim License. The Plan provides direction to Alberta Environment
staff for operation of the water management system to ensure the objectives
of the project continue to be met.
The
Operations Plan has been developed in consultation with landowners,
stakeholders and interested members of the public through ongoing Advisory
Committee meetings, as well as a series of stakeholder meetings and public
open houses.
SYSTEM DESCRIPTION
The Parlby
Creek-Buffalo Lake Water Management system consists of two major components.
the Parlby Creek portion acts as the water conveyance system to divert water
from the Red Deer River into Buffalo Lake. Buffalo Lake is the receiving
waterbody that makes up the second component of the
system.
The water management system
includes:
 |
A pumphouse
to withdraw water from the Red Deer River,
|
 |
a pipeline
and conduit system which conveys the pumped water to a series of small lakes
and ultimately to Alix Lake,
|
 |
a 20
kilometer long Parlby Creek channel which transports water from Alix Lake
through several control structures to Buffalo Lake,
|
 |
a fixed crest
weir at the Buffalo Lake outlet which, when over-topped, allows water to
enter Tail Creek and flow back to Red Deer River.
|
OBJECTIVES OF SYSTEM
The Parlby
Creek-Buffalo Lake Water Management system is a multi-use water management
project with several specific objectives:
 |
Provision of
agricultural flood control,
|
 |
Provision of
a water source for fish and wildlife enhancement.
|
 |
Provision of
municipal water supplies,
|
 |
Stabilization
of water levels in Buffalo Lake.
|
Operation of
the system will work towards balancing the objectives that guided
development of the project.
ADVISORY COMMITTEES
Spotted Lake/Mirror Advisory Committee
- The Spotted Lake/Advisory Committee
provides advice to Alberta Environment on the multi-use operation and
maintenance of the Parlby Creek component of the system. The committee
focuses particularly on the operation of the Carlyle, Spotted Lake and
Mirror structures
Committee
members represent local landowners, with participation of staff from Alberta
Agriculture, Alberta Public Lands, Alberta Fish & Wildlife and Alberta
Environment. Liaison is maintained between the Spotted Lake/Mirror Committee
and the Buffalo Lake Management Team. The committee has been operating since
1987, and generally meets once or twice per year.
Buffalo Lake Management Team -
The Buffalo Lake Management Team was formed
by the Minister of Environment in 1991 to provide advice on the
construction, mitigation and operation of the Parlby Creek-Buffalo Lake
Water Management Project. Since completion of the construction phase of the
project, the Committee focuses on completion of mitigation measures, ongoing
operations, monitoring and land use surrounding the Parlby Creek-Buffalo
Lake system.
The
management team is made up of representatives of the surrounding community,
surrounding counties and Alberta Environment. During the
construction phase, the Committee met monthly. The number of meetings will
likely decrease now that the project has moved into the operational phase.
OPERATIONS GUIDELINES
The following
guidelines will direct the "normal" operation of the Parlby Creek-Buffalo
Lake water management system. Extreme weather conditions such as periods of
extended drought or severe flooding may require operations to proceed
outside the normal guidelines.
Red Deer River Diversion Pumps, Pipeline
and Conduit System
Two
electrical diversion pumps are located in the pumphouse on the Red Deer River south of the Village of Alix. The smaller pump has a capacity of 12.5
cubic feet per second (12.5 cfs), and the larger pump capacity is 37.5 cfs.
The pumps can be operated simultaneously or individually. The Interim
License for the Project authorizes a rate of diversion of 50 cfs from the Red
Deer River.
The pipeline
and conduit system conveys water from the pumphouse on the Red Deer River
to a series of small lakes and eventually into Alex Lake.
Pumping Season -
Pumping will occur during the open water season, starting on or around May 1
and continuing until around Oct 31 each year. Operation of the pumps is
subject to Red Deer River water quantity and quality, the water levels in
Buffalo Lake, or possible flood events within the system.
Residual Flow -
when the pumps are in operation, a residual flow in the Red Deer River must
be maintained at a minimum of 300 cfs downstream of the intake site.
Water Quality -
Pumping will not occur during periods of high flow in the Red Deer River
when there is a significant silt load in the river. High silt content in the
river rapidly deteriorates the pumping system, and deposits material in the
channels and waterbodies along the system.
Fish screen -
during pumping operation, a fish screen will be kept in place to avoid the
transfer of fish from the Red Deer River into the Parlby Creek-Buffalo Lake
system.
Water Volume Monitoring -
The volume of water diverted from the Red Deer River will be monitored and
reported to the Controller of Water Resources each year, including the
periods and rates of diversion.
Power Supply Costs -
Operation of the electrical water diversion pumps is subject to contract
requirements with the power supplier. At present, contract conditions
require that the Department pay costs based on the peak demand on the system
within a calendar month. Operation of the pumps for a few days within a
month results in very high charges and is not considered cost effective. The
high cost factor makes it more practical to operate the pumps for most of a
month, not short periods of time. Contract conditions for power supply any
may change due to recent deregulation of the power industry in Alberta.
Lakes A, B and C Gates -
Lake B outlet structure is a gated control
structure designed to safely pass pumped flows and maintain Lakes B and C
levels. The structure will be kept closed during the winter months.
The gate on the outlet to Lake B is closed during the winter months to
accommodate stock watering.
Alix Lake Control Structure and Spillway -
The water level in Alix Lake will be maintained during the open water season
for recreational benefits to the Village of Alix. The structure is a
self-regulating upstream control structure designed to maintain Alix Lake
level at elevation 790.35 with an emergency overflow for flood events.
Water levels in Alix Lake will be monitored regularly during the open water
season.
Parlby Creek Conveyance System
The Parlby
Creek Conveyance System starts where the water flows over the Alix Lake
Control Structure into the Parlby Creek channel and through several control
structures to Buffalo Lake. The control structures below Alix Lake include a
gate for the Wildlife Conservation Area, and the Mirror, Spotted Lake and
Carlyle backflood control structures.
Annual
operating procedures for backflooding along Parlby Creek are developed by
the Spotted Lake-Mirror Advisory Committee with recognition that Parlby
Creek license priorities guarantee water use for the three backflood
operations involved. The Carlyle backflood has priority up to the limit of
its license (120 acre-feet), followed by Spotted Lake and finally Mirror.
Michael Meehan Diversion -
The Meehan diversion is a pumping system that diverts water from Parlby
Creek to provide for an agricultural backflood. The diversion license is a
senior license that pre-dates development of the Parlby Creek-Buffalo Lake
Water Management System.
Wildlife Conservation Wetland Area Structure
- The structure along Parlby Creek allows
water to flow into the Conservation Area to allow management of water levels
to maintain the quality of the wetland habitat in the area. The structure
may be opened during the Mirror backflood. Once the backflood is
completed, the structure will be closed to retain the water in the Wetland
Area. The gate is operated by Ducks Unlimited under agreement with Alberta
Environment.
Mirror Structure -
The structure is operated to provide moisture in hay lands to boost hay
production and provide wildlife habitat. Flood easements with landowners
affected by the Mirror Structure allow the land to "periodically backflood
to a maximum elevation of 787.3 metres for a duration not to exceed 30
consecutive days per year"
The Mirror
Structure will be closed before spring runoff to allow water to back up in
the flood easement area. The structure will then be opened in mid April to
allow time for the land to dry out to accommodate hay production. The actual
release timing will be closely monitored relative to pike spawning activity
in the Parlby system, but the total duration for backflooding is limited to
30 consecutive days by easement agreements.
Upon
completion of the backflood each year, the structure is left open to allow
the passage of water from any major rainfalls.
Mirror Fish Pond -
The structure is operating each year to pump
water from Parlby Creek into the fishpond or lagoon at Mirror.
Spotted Lake Structure -
The structure is also operated to provide moisture in hay lands to boost hay
production, while providing water for pike spawning and hatching, as well as
wildlife habitat. Flood easements with landowners affected by the Spotted
Lake Structure allow the land to "periodically backflood to a maximum
elevation of 785.8 metres for a duration not to exceed 60 consecutive days
per year"
Spotted Lake
Structure will be closed to coincide with the release of water from the
Mirror Structure (mid-April). Spotted Lake will be raised to as high as the
available water allows, not exceeding the Full Supply Level (785.8). The
high water level will be maintained for a brief period (2-7 days) to
maximize flooding of the hay lands, then dropped to a stable level elevation
(approximately 785.0) for one month until approximately mid-May to
accommodate pike spawning and hatching. Over the next two weeks, until the
end of May, the water is slowly
released to the Crown land boundary (784.0) to accommodate the return of
pike hatchlings to Buffalo Lake. Water must be reduced to Crown boundary by
May 31 to accommodate hay production.
After the
backflooding, the gates in the Spotted Lake Structure may be operated to
retain water at the Crown boundary.
Hamlet of Mirror Water Supply -
The Hamlet of Mirror has access to the water diverted from the Red Deer
River for their domestic water supply. The Hamlet pumps water from Parlby
Creek into a reservoir twice per year during the open water season (May 1 to
October 31).
Carlyle Structure -
The structure is also operated to provide
increased moisture in hay lands to boost hay production and to allow passage
of pike into Spotted Lake for spawning. Timing of the operation of the
Carlyle Structure is dependent of the fish movements each year. The
operation of the gates is done by the landowner through an agreement with
the department.
The Carlyle
Structure has a senior license that take precedent for backflooding for 120
acre-feet. However, the department and landowner have informally agreed to
operate the gates in a manner conducive to the passage of pike, which also
allows more flexibility for the landowner to backflood his property.
Upon
completion of the backflood each year, the Carlyle structure is left open
to allow the passage of water from any major rainfalls.
Lateral drains -
Gated lateral drains are located along the conveyance system to accommodate
natural flows and passage of backflood waters to and from the Parlby
system. Landowners are responsible for the operations of the gates to
control flow onto and off of their property. The Department is the
owner of the lateral drains and gates and
responsible for outgoing maintenance.
Parlby Creek Channel Maintenance -
The Parlby Creek Channel will be maintained by the Department to accommodate
the efficient conveyance of water. Aquatic weed growth will be monitored
regularly in the channel. The
Department will control weeds in an environmentally approved manner.
Parlby Creek Right of Way -
The right of way will be monitored for terrestrial weed growth and control
measures implemented as necessary. Maintenance of the fencing along the
right of way is a shared responsibility between the Department and adjacent
landowners.
Farm Crossings -
Farm crossing are located along the Parlby system to allow access to
farmland bisected by the channel. Maintenance of the farm crossing is the
responsibility of the Department.
Buffalo Lake Component
The Buffalo
Lake Component of the water management project includes Buffalo Lake,
Rockeling Bay Rider Lake, Trail Tail Creek Weir and Channel. The water diverted
from the Red Deer River enters the lake at Parlby Bay and then flows through
the Narrows into the main portion of Buffalo Lake. Water from Buffalo Lake
could flow into Rockeling Bay and Rider Lake in the northeast end of the
lake. Tail Creek is the outlet of Buffalo Lake that flows into the Red Deer
River.
Buffalo Lake Water Levels -
Diversion of water from the Red Deer River will occur until the water levels
in Buffalo Lake reach the elevation of 780.85. Once the maximum elevation
has been reached, pumping will stop until lake levels recede to 780.65. The
fluctuation of 20 cm is intended to encourage a diversity of aquatic plant
growth along the shoreline of Buffalo Lake. The pumping program will
re-initiated once the lake level drops to the lower elevation (780.65).
Water
diversion from the Red Deer River may occur when the lake is at Full Supply
Level (780.85) in order to meet needs for community water supply, backflooding, or fish and wildlife benefits along the Parlby Creek component of
the system.
Rockeling Bay Structure -
Rockeling Bay and Rider Lake are located in
the northeast corner of Buffalo Lake. At higher water levels, water can flow
between Buffalo Lake and Rockeling Bay. The wetlands located on Rockeling
Bay and Rider Lake support a breeding population of endangered piping
plovers and several waterfowl species.
The North
American Waterfowl Management Plan and their agent, Ducks Unlimited,
proposed the construction of a water conveyance works from Buffalo Lake into Rockeling Bay and Rider Lake. At present the Rockeling Bay - Rider Lake
project has been delayed because flood easements have not been completed
with all affected landowners.
A water
control structure will be placed on the channel from Buffalo Lake into
Rockeling Bay. The structure will be kept closed to stop water flowing from
Buffalo Lake into Rockeling Bay. In the event that flood easements can be
secured, the Rockeling Bay control structure could be operated to
periodically allow water to flow into Rockeling Bay when Buffalo Lake is at
elevation 780.85. It is anticipated that flooding of Rockeling Bay and Rider Lake would
occur only once every second or third year.
Tail Creek Structure -
the structure is a sheet pile fixed crest
weir that controls the water level in Buffalo Lake at the elevation 780.85.
The weir is designed at a fixed elevation and cannot be operated to affect
water levels in the lake. In the event of water levels above 780.65, the
water will spill over the weir and flow into the Red Deer River via Tail
Creek.
Tail Creek Channel Maintenance -
The channel of Tail Creek below Buffalo Lake will be monitored and
maintained to allow water passage during periods of high water levels
Tail Creek Channel Right of Way -
The right of way will be monitored for terrestrial weed growth and control
measures implemented as necessary. Maintenance of the fencing along
the right of way is a shared responsibility between the Department and
adjacent landowners.
Farm Crossings -
Farm crossing are located along Tail Creek
to allow access to farmland bisected by the channel. Maintenance of the farm
crossing is the responsibility of the Department.
RESPONSE TO FLOOD EVENTS
Parlby Creek Portion -
When the diversion pumps are operating, a
major rainstorm in the Parlby Creek drainage area could result in flooding
within the system. In the event of a major storm event, all pumping will be
stopped until the natural water flows have returned to normal levels.
Instrumentation along Parlby Creek is monitored to manage channel flows and
local rainfall.
The Mirror,
Spotted and Carlyle structures are usually left open after the backflood is
completed to accommodate any potential flood events.
Buffalo Lake Portion -
If a major storm event or events cause the lake to exceed 780.85 when the
pumps are in operation, the pumping program will stop until water levels
have receded to 780.65.
The 1:100
Year flood elevation for Buffalo Lake has been calculated to be 781.2. The
Province of Alberta acquired shoreline around the lake to provide protection
to the elevation 781.2.
The
Tail Creek weir is a fixed crest weir at 780.85 and is designed to pass the 1:100
year flood. The Department has no ability to mitigate flooding events on
Buffalo Lake by releasing additional water over the weir.
WATER WITHDRAWALS
The Parlby
Creek-Buffalo Lake Water Management project may not be able to maintain the
target water levels in Buffalo Lake during various weather and lake level
conditions, primarily due to evaporation. However, applications to divert or
withdraw from the system which do not fall within the objectives for the
project (see Page 2) should be evaluated under the conditions stated below.
Category 1
Withdrawal projects that are located
upstream of Buffalo Lake (Parlby Bay) may be considered based on historical
natural flows that existed before the Parlby Creek-Buffalo Lake Water
Management project was implemented.
Category 2
Projects for domestic and small stockwatering (5 acre-feet or less per year) may be considered and
evaluated.
Applicants
for domestic, municipal, and agricultural uses for 5 acres feet or less may
be approved unless it can be determined that they would have a negative
impact on downstream license holders for riparian water users.
Applicants
that could potentially benefit from the pumping scheme would only be considered
if they can live with the following conditions:
Priority
for water from the project is to meet the needs of;
 |
The
municipalities of Mirror and Alix,
|
 |
The backflood schemes for Spotted Lake, Mirror, and Carlyle,
|
 |
The
stabilization of Buffalo Lake.
|
Applications
may be considered only when the above needs are met. Water that could be
made available would be considered on a cost recovery basis. The priority
requirements suggest that new applicants would have to evaluate the
economics of their project to accommodate storage of water for periods when
they would not be allowed to pump. Storage of enough water for three or four
years may be necessary.
Groundwater
applications that could impact surface water would have to meet the surface
water condition listed above. The groundwater requirements are intended to
prevent applicants from drilling in area close to a waterbody and
effectively getting water from the surface water source.
Category 3
Water withdrawal projects located in the
non-contributing areas of the basin may be considered.
Projects in
non-contributing area of the basin where water would not normally get to the
lake except in extremely wet years may be considered on their own merits and
considered for licensing.
Category 4
Water withdrawal projects that require water
to be taken directly from Buffalo Lake should not be considered.
MAINTENANCE OF MITIGATION
PROJECTS
Maintenance
of specific mitigation projects is negotiated with local authorities and
other partners.
MONITORING
Water Levels -
An automatic gauging station at Rochon Sands monitors the water levels in
Buffalo Lake.
Lake Water Quality Monitoring -
Lake water quality will be monitored on an ongoing basis.
PLAN REVIEW
The
Operations Plan for the Parlby Creek-Buffalo Lake Water Management System
will be formally reviewed 10 years after approval. Major changes or extreme
weather conditions may require a review of operations in a particular year.
The Buffalo Lake Management Team and the Spotted Lake-Mirror Advisory
Committee can assist the Department to assess the need for review of the
Operations Plan.
|
|
|